Can a Contractor Recover Costs for Delays Caused by Late Design Approvals? – The Pinnacle List

Can a Contractor Recover Costs for Delays Caused by Late Design Approvals?

Yes. A contractor may be able to recover additional costs when late design approvals delay construction, but recovery depends on the contract terms, the cause of the delay, and the contractor’s ability to document the resulting losses. A contract may allow extra time, additional payment, or both when the owner or design team causes an avoidable delay.

Houston is one of the most famous cities in Texas, US. Houston construction projects often involve multiple parties, including property owners, general contractors, architects, engineers, and subcontractors. Design approvals can affect the timing of materials, labor, inspections, and other scheduled work. When approval delays disrupt a project, a Houston construction attorney can help assess the contract and the available remedies.

How Late Design Approvals Affect Construction Costs

Contractors rely on approved drawings, specifications, and submittals before completing many stages of construction. If an architect or owner takes longer than the contract allows to review a submission, the contractor may have to postpone work or change the project schedule.

These delays can create additional expenses, including:

  • Labor costs for workers who cannot proceed with scheduled tasks.
  • Equipment rental charges during periods of inactivity.
  • Extended site supervision and project management expenses.
  • Storage fees for materials awaiting approval.
  • Additional costs caused by rescheduling subcontractors.
  • Increased material prices if procurement is pushed back.

A contractor must connect these costs to the approval delay. Expenses that would have occurred regardless of the delay may not qualify as recoverable damages.

What the Construction Contract Says Matters

The contract is usually the starting point for determining whether a contractor can recover delay-related expenses. It may set deadlines for reviewing design submissions, explain how approval requests must be made, and describe the remedies available when a delay occurs.

Some contracts allow extensions of the completion date for excusable delays but do not provide additional money. Others permit adjustments to both the project schedule and contract price when the delay results from the owner’s actions or another specified cause.

A no-damages-for-delay clause may also limit financial recovery. However, its wording, scope, and enforceability must be considered alongside other contract provisions and applicable law.

Proving That Late Approval Caused the Delay

A contractor should be able to show when a design submission was delivered, when a response was required, and when approval was actually received. The contractor must also explain how the delay affected the project schedule and created additional costs.

Useful documentation includes:

  • Original and updated construction schedules.
  • Design submittals and approval records.
  • Requests for information and written responses.
  • Meeting minutes and project correspondence.
  • Daily construction reports and labor records.
  • Equipment rental invoices and subcontractor statements.
  • Change orders and payment applications.

A schedule analysis may help demonstrate whether the approval delay affected the project’s critical path. This is important because not every late response delays the final completion date.

Texas Law and Contractual Remedies

Texas law generally allows parties to pursue remedies for breach of a construction contract, subject to the contract’s terms and applicable legal restrictions. Texas Civil Practice and Remedies Code § 38.001 may allow a party to recover reasonable attorney’s fees in certain successful contract claims.

The Texas Supreme Court’s decision in Pepper Lawson Horizon International Group, LLC v. Texas Southern University (2023) illustrates why the exact contract language matters. The dispute involved claimed excusable delays, design-related issues, contract adjustments, and provisions governing additional time and costs. The decision shows that a contractor must establish its rights under the actual contract rather than assume every delay automatically creates a right to payment.

Steps Contractors Should Take When Approvals Are Delayed

Contractors should notify the owner or designated representative as soon as an approval delay affects the work. Notices should follow the method and deadlines specified in the contract.

They should also update project schedules, identify affected activities, and keep a clear record of additional expenses. Continuing work without documenting the impact can make it harder to establish the connection between the delay and the claimed costs.

Pro Tip: Submit written delay notices promptly, even when the full financial impact is not yet known. Waiting until project completion may create disputes over whether the contractor complied with the contract’s notice requirements.

FAQs

1. Can a contractor claim labor costs caused by late design approvals?

Potentially. The contractor must show that the delay caused additional labor expenses and that the contract or applicable law allows recovery.

2. Does every late approval qualify as a compensable delay?

No. The delay must generally affect the work or project schedule, and the contractor must establish that the claimed costs resulted from it.

3. Can a contractor request more time instead of additional money?

Yes. Some contracts allow an extension of the completion date without providing financial compensation. The available remedy depends on the contract language.